Senate Passes Permitting Reform Bill: What It Means for Clean Water Act Permits and Environmental Reviews
On November 19, 2026, the U.S. Senate passed the Bipartisan American Affordability and Jobs Act of 2026 (BAAJA) as a substitute amendment to H.R. 2347. BAAJA would amend several federal statutes that govern the permitting of infrastructure, energy, and development projects, including the Clean Water Act (CWA), 33 U.S.C. § 1251 et seq.; the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq.; the Endangered Species Act (ESA), 16 U.S.C. § 1531 et seq.; and the National Historic Preservation Act (NHPA), 54 U.S.C. § 300101 et seq. BAAJA would also impose new agency deadlines and limit how and when project approvals may be challenged in court. BAAJA is not yet law; the House must still act on the Senate’s version, which it could amend further, and the President must sign the final bill to become law.
BAAJA’s Key Elements
Section 401 water quality certification would be subject to a clear and convincing evidence standard and firm deadlines.
An applicant for a federal permit or license for an activity that would result in a discharge into “waters of the United States” (WOTUS), such as a U.S. Army Corps of Engineers (USACE) dredge-and-fill permit under CWA § 404, 33 U.S.C. § 1344, must first obtain under CWA § 401, 33 U.S.C. § 1341, a certification that the discharge will comply with water quality requirements from the “certifying authority,” which BAAJA would define as the state or interstate agency to which the application is submitted (including a tribe treated as a state under 40 C.F.R. § 131.8) or, where none has authority, the U.S. Environmental Protection Agency (EPA). A denial generally prevents the federal permit from being issued. Under BAAJA, review would be limited to water quality requirements, and the certifying authority could deny certification only if it determines, by clear and convincing evidence, that no modification or reasonable condition would allow the project to comply, or that the application remains incomplete after the applicant has had a reasonable opportunity to supply missing materials. Each condition would have to meet the same standard and be the least burdensome necessary to ensure compliance with water quality requirements. If a denial or condition is litigated, the certifying authority, rather than the applicant, would bear that burden of proof. The federal licensing or permitting agency, in consultation with the certifying authority, would set a reasonable period for final action on the application (grant, grant with conditions, deny, or waive) of no more than one year from receipt (nine months for direct point source discharges from Natural Gas Act § 7 pipelines and bulk-power system transmission projects). If the certifying authority fails to act within that period, certification would be waived unless the applicant requests, and the certifying authority agrees in writing to, an extension.
CWA § 402 NPDES permits could last up to ten years, and WOTUS rules would be reviewed directly in the court of appeals with jurisdiction.
Pursuant to CWA § 301, a facility that discharges pollutants from a point source (such as a pipe or outfall) into WOTUS generally must obtain a CWA § 402 National Pollutant Discharge Elimination System (NPDES) permit. NPDES permits have a maximum five-year term; BAAJA would extend that maximum term to ten years. BAAJA would also require EPA to adopt water quality criteria through notice-and-comment rulemaking and would send challenges to those criteria, and to EPA rules defining WOTUS, directly to the federal court of appeals with jurisdiction. BAAJA would not itself change the WOTUS definition, which has been the subject of varying and confusing rulemakings and litigation for decades.
Section 404 permits would provide longer and more secure coverage.
CWA § 404 requires a USACE permit to discharge dredged or fill material into WOTUS, including many wetlands and streams. Smaller scale impacts often associated with certain designated development or infrastructure projects and activities may proceed under general permits, including nationwide permits (NWPs), rather than individual permits. BAAJA would extend Section 404 general permit terms from five to ten years, deem discharges into less than two acres as having only minimal effects, and require USACE to maintain NWPs 12, 14, 27, 43, 57, and 58 for discharges into less than two acres per project. For applications submitted after enactment, EPA could exercise its Section 404(c) “veto” authority to prohibit or restrict a dredge spoils disposal site only between submission of a complete application and permit issuance, foreclosing such veto after permit issuance.
Section 404 challenges would be subject to a 150-day deadline and limited remedies.
Challenges to Section 404 permits and general-permit verifications generally would have to be filed within 150 days. Where a draft permit is published in the Federal Register with a comment period of at least 30 days occurring after enactment, only parties that raised the issue in sufficiently detailed comments on the proposed permit could sue. That limitation would not apply to NWP coverage determinations that are not subject to such a public-comment period, but the 150-day deadline would still apply. A court could not vacate, enjoin, or otherwise limit a permit or verified activity unless the permitted activity would present an imminent and substantial danger to human health or the environment for which no other equitable remedy is available.
NEPA would be confirmed as procedural and subject to firm review deadlines
NEPA requires federal agencies to evaluate the environmental effects of major federal actions, including many permits, through an environmental assessment (EA) or a more detailed environmental impact statement (EIS). BAAJA would provide that NEPA establishes a procedure and does not mandate any particular outcome. At a project sponsor’s request, agencies would have to consider relying on existing federal, state, or tribal analyses, and no NEPA document would be required where the lead agency determines that a state or tribal review, or compliance with another federal law, serves a similar function. Lead agencies would have one year to complete an EA and two years to complete an EIS. After an EIS is published, the lead agency would have 45 days to issue a record of decision, and other agencies would have 90 to 120 days to act on remaining approvals.
NEPA challenges would be subject to a 150-day deadline, direct appellate review, and limited remedies.
NEPA claims generally would have to be filed within 150 days by parties that submitted sufficiently detailed comments on the issue (where the comment period occurs after enactment), and most would proceed directly in the federal court of appeals for the circuit where the project is located. If a court finds a violation, it generally could only remand the approval for correction within 180 days, and the project could proceed during remand. Preliminary injunctions would be available only in limited circumstances and only for violations of laws other than NEPA and the NHPA.
ESA Section 7 consultation would be shorter and aligned with NEPA.
A federal agency that permits, funds, or carries out an action that may affect a threatened or endangered species must consult with the U.S. Fish and Wildlife Service or the National Marine Fisheries Service, a process that concludes with a biological opinion. BAAJA would shorten formal consultation from 90 to 60 days and allow applicants to seek judicial relief if an extension would exceed 145 days without a written statement to the applicant or the applicant’s consent. Where an EA or EIS is required, BAAJA would generally require consultation to be completed by the NEPA completion deadline for that document—that is, by the date the EA is completed and made public or, for an EIS, the date the final EIS is published. It would also exempt certain transportation projects in operational rights-of-way, and challenges to biological opinions generally would have to be filed in the D.C. Circuit within 150 days after the opinion is made public.
NHPA Section 106 review would be narrower and tied to the NEPA schedule.
Section 106 requires federal agencies to consider the effects of their permits, funding, and actions on historic properties and resources. BAAJA would exclude several categories of activities from review, including certain financial-assistance-only projects and minor or routine repair and maintenance, and would limit review to historic properties within the area of potential effects identified by the permitting agency. For projects requiring an EA or EIS, consultation would have to begin when NEPA review begins and would generally have to be completed when the EA is completed and made public or the final EIS is published. As under NEPA, a court finding a violation generally could only remand the matter for correction within 180 days. Federal agencies would remain obligated under the Section 106 process to consult with tribes as to the potential impacts on historic resources.
Do Not Forget About State/Local Programs
Regulated parties should keep in mind that most states, and some regional and local jurisdictions, administer the CWA § 402 NPDES program under EPA authorization. These programs must be at least as stringent as the federal program, and the CWA and NPDES regulations allow them to be more stringent. In addition, certain states (like Virginia) have their own state-law permitting programs for impacts to surface waters, including wetlands, that overlap with or are more stringent than the USACE and EPA § 404 program, or that reach waters beyond WOTUS. So, while BAAJA may provide welcome relief at the federal level, state programs may not necessarily follow suit. Regulated parties should therefore track applicable state permitting and water quality standards programs regardless of BAAJA and, where needed, be prepared to pursue a parallel state permitting track for the same activity, with potentially different procedures and outcomes.
Looking Forward
If enacted as currently passed by the Senate, BAAJA would require each federal agency to revise its NEPA regulations and procedures within 180 days, and, beginning December 31, 2027, a certifying authority that has not adopted rules specifying additional Section 401 application materials would have to treat an application as complete if it contains the basic information BAAJA specifies. BAAJA could shorten permitting timelines and reduce litigation risk for many projects, but, because the final legislation may differ, developers, utilities, and other permittees should monitor its fate closely and consult legal counsel regarding how it may affect their pending or planned projects.
Key Takeaways
- Clean Water Act Permitting Changes – BAAJA would establish stricter standards and deadlines for Section 401 certifications and extend the maximum terms for certain water discharge and dredge-and-fill permits.
- Streamlined NEPA Reviews – The legislation would set one-year deadlines for environmental assessments and two-year deadlines for environmental impact statements, while allowing greater reliance on existing environmental reviews.
- Limits on Environmental Litigation – BAAJA would generally require challenges to certain Clean Water Act and NEPA approvals to be filed within 150 days and limit available court remedies.
- Shortened Environmental Reviews – The legislation would shorten Endangered Species Act consultations from 90 to 60 days and align certain historic preservation reviews with NEPA timelines.
- State and Local Permitting Requirements – Federal permitting changes would not necessarily extend to state and local programs, which may maintain separate or more stringent requirements.
- Senate Passage Is Not the Final Step – BAAJA’s passage in the Senate is significant, but the bill remains subject to House approval and potential further amendment before final legislation can be presented to the President for signature and enactment.